A public utility district is expanding a colocation data center and needed project management to coordinate electrical, HVAC, and connectivity work inside a live facility. Our team serves as the district's project manager and single point of contact:
- Developed and maintain the consolidated project schedule
- Supported the HVAC RFP, contractor evaluation, and award
- Developed the zero-outage equipment cutover plan
- Track permits, closeout, and documentation
The facility stays online while the expansion goes in around it.
SCHEDULE AND COORDINATION
One schedule covers the electrical, HVAC, and connectivity contractors. Trades are sequenced so work in the operating facility never conflicts.
PROCUREMENT SUPPORT
Our team supported purchasing with the HVAC RFP, evaluated the bids, and made the award recommendation.
Site work was placed ahead of the equipment deliveries.


CUTOVER PLANNING
The cutover plan moves equipment onto the new infrastructure with zero outage. Sequencing is coordinated with the network operations center, the tenant, and connectivity providers around uptime requirements and blackout windows.
CLOSEOUT
Permits are tracked through final inspection. Manufacturer documentation and as-builts are compiled, and contractors are briefed on facility protocols including fire suppression and hot work.
BOTTOM LINE
- A district needed its data center expansion coordinated without risking uptime
- Our team manages the schedule, contractors, cutover, and closeout as a single point of contact